LOCATION: Carole Park, QLD
CLIENT: FIFE Capital
VALUE: $18 Million
ROLE:

The purpose built industrial facility for Maxitrans, a large supplier of heavy duty road transport trailers, is one of three facilities being constructed within FIFE Capitals’ Silica Street Industrial Estate.

The Maxitrans warehouse development consisted of a 11,000m2 factory assembly line space and 2,200m2 parts warehouse storage, 1,300m2 office space and amenities over two levels, with loading areas and parking for 188 cars.  The project required a Change Application to the original DA which was undertaken concurrently with services authority and operational works design and approvals, prior to a D&C tender.  Bulk earthworks commenced in July 2019 and the project was handed over in September 2020.